Course Information

Course Information
Course Title Code Semester L+U Hour Credits ECTS
- IKS2103 3. Semester 3 + 1 4.0 4.0
Prerequisite Courses None
Language of Instruction Turkish
Course Level Associate
Course Type
Mode of delivery Face To Face
Course Coordinator
Instructor(s) Ali Etem GÜREL
Assistants
Goals Knowing, designing and designing ventilation and air conditioning systems to ensure that the project is carried out
Course Content 1 - Equipment used in Ventilation and Air Conditioning systems to recognise 2 - Selection of necessary equipment in Ventilation and Air Conditioning systems to ensure 3 - Required flow rate and duct for ventilation and air conditioning systems To project the system by making calculations of diameter etc.
Learning Outcomes - Equipment used in ventilation and air conditioning systems to recognise
- Makes cold room project.
- Selection of cold room equipments
- Selection of necessary equipment in ventilation and air conditioning systems to ensure
- Required flow rate and ducts for ventilation and air conditioning systems To project the system by making calculations of diameter etc.
- calculation of pipe diameters and its assembly
Lesson Plan (Weekly Topics)
Week Topics/Applications Method
1. Week Defining ventilation, specifying ventilation methods Preparation, After Class Study Practice Other Activities Research Course Hours
1. Week Basic concepts Preparation, After Class Study Course Hours
2. Week Industrial cooling systems and cold rooms Course Hours Preparation, After Class Study
2. Week Defining fans and their types specifying Practice Research Other Activities Preparation, After Class Study Course Hours
3. Week Examination of fan laws, pressure temperature, Explanation of flow concepts Other Activities Practice Research Preparation, After Class Study Course Hours
3. Week Cooling load calculation Preparation, After Class Study Course Hours
4. Week Cooling load calculation Preparation, After Class Study Course Hours
4. Week Calculation to determine the need for fresh air explanation of methods Other Activities Research Preparation, After Class Study Practice Course Hours
5. Week Calculation of ventilation duct cross-section Preparation, After Class Study Other Activities Research Practice Course Hours
5. Week Selection of circuit elements Course Hours Preparation, After Class Study
6. Week Selection of circuit elements Preparation, After Class Study Course Hours
6. Week Calculation of ventilation duct cross-section
7. Week Calculation of ventilation duct cross-section Course Hours Preparation, After Class Study Research Practice Other Activities
7. Week Calculation of pipe diameter Preparation, After Class Study Course Hours
8. Week Calculation of pipe diameter Course Hours Preparation, After Class Study
8. Week Grille used in ventilation systems, Providing information about equipment such as dumpers etc. Preparation, After Class Study Research Practice Other Activities Course Hours
9. Week Information about different ventilation systems giving Preparation, After Class Study Research Other Activities Practice Course Hours
9. Week Cold room installation Course Hours Practice Research Preparation, After Class Study Other Activities
10. Week Cold room installation Other Activities Research Practice Preparation, After Class Study Course Hours
10. Week Variable fluid flow (VRF) systems Providing information about Research Other Activities Preparation, After Class Study Course Hours Practice
11. Week Variable fluid flow (VRF) systems Providing information about Practice Research Preparation, After Class Study Other Activities Course Hours
11. Week Cold room installation Course Hours Other Activities Practice Research Preparation, After Class Study
12. Week Operation, maintenance and repair of the cold rooms Preparation, After Class Study Course Hours
12. Week air handling unit Other Activities Research Preparation, After Class Study Practice Course Hours
13. Week Roof type air conditioners Argument Preparation, After Class Study Course Hours Other Activities Practice Research
13. Week Technical tour (ISK SODEX) Preparation, After Class Study Course Hours
14. Week Operation, maintenance and repair of the cold rooms Preparation, After Class Study Course Hours
14. Week Duct type air conditioning systems Practice Research Preparation, After Class Study Course Hours Other Activities
Recommended Sources
Havalandırma ve İklimlendirme Esasları Hikmet Doğan Seçkin Yayıncılık
Uygulamalı Havalandırma ve İklimlendirme Tekniği Hikmet Doğan Seçkin Yayıncılık HAVALANDIRMA TESİSATI MMO/297
“Soğutma Tesisatı”, MMO Yayınları Yayın No: 295/5.
“Soğutma Tekniği ve Isı Pompası Uygulamaları”, Recep YAMANKARADENİZ, İlhami HORUZ, Ömer KAYNAKLI, Salih COŞKUN, Nurettin YAMANKARADENİZ., Dora YAYINCILIK, 2009.
“Air Conditioning and Refrigeration”, Rex MILLER, Mark R. MILLER., McGraw-Hill, 2006.
Relations with Education Attainment Program Course Competencies
Program Requirements Contribution Level DK1 DK2 DK3 DK4 DK5 DK6 Measurement Method
PY3 3 0 0 0 0 0 0 -
PY4 3 0 0 0 0 0 0 -
PY5 3 0 0 0 0 0 0 -
PY6 4 0 0 0 0 0 0 -
PY8 5 0 0 0 0 0 0 -
PY9 5 0 0 0 0 0 0 -
PY10 4 0 0 0 0 0 0 -
PY12 4 0 0 0 0 0 0 -
PY14 4 0 0 0 0 0 0 -
PY15 4 0 0 0 0 0 0 -
*DK = Course's Contrubution.
0 1 2 3 4 5
Course's Level of contribution None Very Low Low Fair High Very High
Method of assessment/evaluation Written exam Oral Exams Assignment/Project Laboratory work Presentation/Seminar
ECTS credits and course workload
Event Quantity Duration (Hour) Total Workload (Hour)
Course Hours 14 4 56
Preparation, After Class Study 1 10 10
Midterm 1 1 13 13
Homework 1 10 1 10
Final 1 13 13
Total Workload 102
ECTS Credit of the Course 4.0